Question: 1 / 185

When may the USACE supervisor decide that temporary project fencing is not required?

Based on the size of the project

Depending on the nature and locations of the project site

The decision regarding whether temporary project fencing is required is primarily contingent upon the nature and locations of the project site. This includes factors such as the proximity of the work area to public access points, potential risks to unauthorized individuals, and the sensitivity of the surrounding environment or community. If the project site is situated in an area where the potential for trespassing is low, or if the activities being conducted do not pose a safety risk to outsiders, a supervisor may determine that fencing is not necessary.

Additionally, the context of the project, including existing barriers and the overall environment, plays a crucial role. For instance, a project located in a remote area where public access is controlled or limited may not necessitate fencing. The supervisor uses their judgment based on these specific characteristics of the site rather than on broader considerations, such as project size or scheduling pressures, which do not directly relate to safety and security concerns.

Get further explanation with Examzify DeepDiveBeta

When the project is behind schedule

If there are no hazardous materials on site